Bastarreche Port - Alicante
Date: 2007
Type of work:Civil Work
Alsina runs the extension of Repsol´s pier for tankers discharge.The project consisted in the construction of a building located in an artificial island connected to the port. To work the formwork, Alsina used 3.500 m3 of CL-40 shoring system which a small part was bracket
above the sea. For the column system implementation it was used Alisply Universal. Given the uniqueness of the project, the material
was used to support the pier and then was transferred to the artificial island. The client was fully satisfi ed with the formwork provided by Alsina.
Alsina systems:
Alisply multipurpose,
Alsina cl-40 shoring system