Peaker Escatron Power Plant – Huesca
Date: 2007
Type of work: Civil engineering
The main difficulty of this project was that it included several levels of beams at height. On each of these levels, the beams were laid out differently, and the last one had beams and a slab. The building process began at the beam level. After three days the columns were made. On the next day, they were stripped and work continued on the next level. The first level was built using Vistaform Slabs. CL-40 Shoring system, recovered from the finished bottom level, plus Vistaform Slabs were used after the second level of beams.
Dowel connections were used to continue raising the shoring system through the successive beam levels. This made it possible to rise up level by level recovering only the Vistaform Slabs without having to remove all the shoring system. The beam support between panels was used to prop up the beams. During the beam stripping process, the supports were propped up with a prop which in turn was resting on the bottom level until they provided the strength required by the project management.
As regards safety, Alsina provided the Alsipercha system, since the layout of the columns on the plan favoured this option. The system was perfectly suitable and received praise from the safety technicians. Finally, 500 linear metres of beams, 2000 m2 of slab and 1000 m2 of wall were built.
Alsina systems:
Alisply walls,
Alispilar,
Alsina cl-40 shoring system,
Alsipercha